- Upon implementation of the block train             ANKARA İSTANBUL
         application in 2004, freight that could be transported   HIGH SPEED RAILWAY PROJECT
         in 15 can now be transported in 3 days which
         provided an 80 percent saving on time.                  Upon completion of the Ankara-İstanbul High
                                                              Speed  Railway Project  which  features  a  double-
            26 BILLION TL INVESTMENT                          tracked, electrified, signal line that allows up to 250
            ON RAILWAYS IN 10 YEARS                           km/h speed, travel time between the two cities will
                                                              be reduced to 3 hours.
            Aiming to turn revive the Ancient Silk Road by
         turning into a Rail Silk Road, the Ministry has made    8 million and 50 thousand people have traveled
         investments on railways over the last decade that  so far in the projects Ankara-Eskişehir section which
         amount to a total of 25 billion 964 million TL.      was opened in 2009. The high speed train has also
                                                              increased passenger activity between Ankara and
            In the next 10 years, a new high speed rail line  Eskişehir and passenger traffic has increased by ten
         of 10 kilometers will be constructed in addition  times after it has opened for service.
         to a 4000-km conventional new track. Planning
         for ‘speedy’ access to many cities in Anatolia, the     Works are ongoing rapidly for the project’s branch
         Ministry of  Transportation, Maritime Affairs, and  that  extends  towards  İstanbul.  Train  service  on
         Communications aims to build a new railway line of  Ankara-Eskişehir is to begin by the year’s end.
         14975 kilometers, with 9978 km of high speed rail line
         and 4997 km of conventional line, by the Republic’s
         centennial.                                             ANKARA-KONYA
                                                                 HIGH SPEED RAILWAY PROJECT
            The current 11 thousand kilometers of railway line
         will double in a decade. Double track length will rise   Ankara-Konya High Speed Railway Project was
         from 9 to 50 percent. And the currently electrified  completed by a local contractor, local engineers,
         track ratio of 26 percent will increase to 60 percent.  and entirely with our own resources. A 212-km high-
                                                              speed rail line was built compatible for 300 km/h
                                                              speed that headed towards the south from Polatlı on
            14 CITIES WILL HAVE YHT IN 5 YEARS                the Ankara-İstanbul project which connected Konya
                                                              with Ankara. Once over, it will connect Konya with
            Binali  Yıldırım, the Minister of  Transportation,  İstanbul as well.
         Maritime Affairs, and Communications, said that
         high speed rail lines were to reach 14 cities in 5 years.
         These cities include Ankara, İstanbul, İzmir, Eskişehir,
         Bursa, Kocaeli, Balıkesir, Konya, Afyonkarahisar, Uşak,